Structural monitoring process for the construction of the martyr Ahmed Hamdi Tunnel 2 project

Stage 1

Customer Name :

Engineering Authority of the Armed Forces.

Tasks :

  • Monitoring the impact of the drilling machine on the surrounding buildings and monitoring the soil movements above the tunnel path using four inclinometers and two extensometers at 30 m depth.

Stage 2

Customer Name :

Engineering Authority of the Armed Forces.

Tasks :

  • Structural safety monitoring of concrete walls of escaping shaft hole using three inclinometers at 60 m depth and follow it-up for a year.

Stage 3

Customer Name :

Engineering Authority of the Armed Forces.

Tasks :

  • Structural safety monitoring of diphram walls exit shaft using ten inclinometers and follow it-up throughout the implementation period.

UG is a sub-contractor of the main contractors (Petrojet & Concord) of the project.

More Projectes

Saudi Arabia

Installation and Follow up of systems for Task Execution Is Monitoring Tower For Detecting The Outside Effects On The Tower Like the Wind Speed And Wind Direction

Saudi Arabia

Makkah Soil Is Hard Rock. So, they use Blasting to Excavate for Foundation. During the Blasting Process, they need to monitor the Surrounded Building to Monitor Any Settlement

Kuwait

Supply complete monitoring solution for testing and monitoring the piles for strain stress along the piles and structure settlement

Sudan

The Task Executed is Installing Hydrological Monitoring Systems Full Complete to Monitoring the all Water Level , Water Quality Parameters , Water Speed