Industrial Area Port Said Egypt - Vertical Drain
Stage 1 : Supply complete monitoring solution for testing and monitoring project trial zone
Customer Name :
Keller Middle East UAE
Tasks :
-
Drilling 11 borehole with depth up to 60 meters include coring and geotechnical sampling.
-
Inclination monitoring in two bore holes by install 60-meter QC inclinometer casing 70mm dia.
-
Installation of 4 piezometers boreholes, each borehole includes 4 sensors installed at depths 60, 45, 25, 15 meters.
-
Installation of 5 magnet extensometer boreholes include 8 magnet's (1 datum magnet, 3 spider magnet, 4 plate magnets) per borehole at depth -50, -35 , -25 , -15 , 0 ,+1.5 , + 3.5 , +5.5 , +7 meters
-
The operation includes the data collection by portable data collectors at interval day by day reading.
Supply complete monitoring solution for testing and monitoring project trial zone by monitoring ( geotechnical water pressure , geotechnical settlement ,geotechnical inclination , the scope include the supply , installation include the boreholes drilling and coring , operation and data representation for period 7 months.